Wind farm site in Liverpool Bay will jump from 10 to 40 square kilometres
A multi-million pound scheme to quadruple the size of the Prestatyn offshore wind farm has moved into its construction phase.
The first of 32 foundations has just been installed at DONG Energy’s Burbo Bank extension in Liverpool Bay, which will increase four-fold, from 10 to 40 square kilometres.
The Danish firm are adding 32 more turbines to the existing 25, which lie 12.2km off Point of Ayr, in a project reported to be worth £450million.
Mono-pile installation
Installation of the first mono-pile foundation has just been finished. It was installed by Van Oord’s heavy-lift vessel ‘Svanen’ – a large floating crane standing 100 metres tall and able to lift more than 8,000 tonnes.
The mono-piles provide the base for the eight megawatt turbines which will be put in later this year.
The project will involve the construction of 32 turbines, marking the first time this size of turbine will be commercially deployed.
DONG Energy has said the site is “ideal for an offshore wind farm,” as it features relatively low water depths, good wind resource and suitable seabed conditions.
Next steps
Over the next few months work will continue to install foundations, prepare for installation of the offshore substation (a buried sea cable which will come ashore between Rhyl and Prestatyn) and lay the cables that will connect the turbines to the national grid connection point at the Bodelwyddan onshore substation in St Asaph.
Then, later in the autumn, work will begin on the installation of the turbines.
The wind farm will have a capacity of 258MW, generating enough electricity to power approximately 230,000 homes, and is expected to be fully commissioned by the end of 2017.
Situated approximately seven kilometres north of the Wirral, the Burbo Bank extension site is one of four offshore wind farms that DONG Energy is currently constructing in the UK.
RYA position
The Royal Yachting Association (RYA) acknowledges the Government’s desire to promote renewable energy, however the governing body for boating is keen to ensure the navigational safety of recreational boating around the coast.
A spokesman said: ‘We have successfully stopped developers from establishing permanent operational safety or exclusion zones around wind farms that would prevent recreational craft from making passage through them.
‘We continue to constantly monitor the developments in Round 3 wind farms and Round 2 extensions – assessing their potential impact on recreational boating.’
Investment confirmed for world’s largest offshore wind farm
Hornsea Project One wind farm will span an area of approximately 407 square kilometres off the Yorkshire coast with up…
Wind farm construction to begin off Sussex coast
The Rampion project is set to become the first offshore wind farm off the south coast of England.
Hornsea Project One offshore wind farm gets the go ahead
The offshore wind farm project for the Yorkshire coast is scheduled to commence operation by 2020
The world’s third largest offshore wind farm gets go-ahead
Thousands of jobs forecast as two adjacent wind farms off the Scottish coast gain formal consent
Plans for £5.4bn wind farm scheme withdrawn
Basking sharks and ground conditions are among the reasons for dropping the Argyll Array Offshore Windfarm proposal
Navitus Bay Wind Park refused development consent
The Department for Energy and Climate Change has announced its decision to refuse development consent for the proposed Navitus Bay…
Navitus Bay wind farm: supporters and opposition speak out
An open floor hearing on the proposed Navitus Bay Wind Park, hosted by the Planning Inspectorate